Two tunnels that will redraw Europe's rail map: Fehmarnbelt and Brenner

A tunnel under the Baltic between Denmark and Germany, and the world's longest underground railway beneath the Alps, will cut hours off some of Europe's key business routes. Both are years late. Here is where they stand in 2026 and what they will change.

A train coming out of a tunnel
Photo: Anastasia Zolotukhina on Unsplash

In short

  • The Fehmarnbelt tunnel will link Denmark and Germany under the Baltic in 18 km. Four of its 89 concrete elements, almost 900 metres, were in place by 28 September 2026.
  • It was due in 2029; its builder now says it will not open before 2031, road first and rail later. Germany's new rail line to it is expected around 2032–33.
  • Once open, Copenhagen–Hamburg should take about two and a half hours by train instead of more than four and a half, and the car crossing about 10 minutes instead of a 45-minute ferry.
  • The Brenner Base Tunnel between Austria and Italy, 55 km long, was dug through at the border in July 2026. It is expected to open at the end of 2032 and cut Innsbruck–Fortezza from 80 to 25 minutes.
  • The weak link is the approach lines, especially in Germany, where the Munich–Brenner upgrade is not expected before the 2040s.

Two of the biggest construction projects in Europe are tunnels that will change how people travel between Scandinavia, Germany and Italy. One runs under the Baltic Sea, the other beneath the Alps. Both will turn slow, awkward journeys into quick train rides, and both are running years behind schedule. Here is what is being built, where things stand in 2026, and what it will mean for business travel.

Fehmarnbelt: Denmark to Germany under the sea

The Fehmarnbelt tunnel will run 18 km between Rødby on the Danish island of Lolland and Puttgarden on the German island of Fehmarn, carrying a four-lane motorway and a two-track electrified railway. It is being built from 89 giant concrete elements, 79 of them 217 metres long, cast in a factory in Denmark, floated out and sunk into a trench in the seabed.

The fourth element went into place on 28 September 2026. That makes almost 900 metres of tunnel so far; 16 standard and three special elements have been cast. Denmark’s construction budget is DKK 52.6 billion, about €7 billion, including reserves, and the EU has contributed around €1.3 billion to the rail parts.

The delays. The tunnel was due to open in 2029. The owner, Sund & Bælt, said in January 2026 that it would not open before 2031, with road traffic first and trains later; a new official timetable is expected once more elements are in place. On the German side, Deutsche Bahn’s new 88 km line from Lübeck to Puttgarden is expected around 2032–33, and a new tunnel to replace the old Fehmarnsund bridge to the mainland is now expected around the end of 2032, with its estimated cost up from €714 million to about €2.3 billion.

What changes. Today trains between Copenhagen and Hamburg go the long way round through Jutland and take around four hours 40 minutes. Through the tunnel the journey should take about two and a half hours, spending only seven minutes under the sea. Drivers will cross in about 10 minutes instead of taking a 45-minute ferry plus waiting time.

Brenner: Austria to Italy beneath the Alps

The Brenner Base Tunnel will run 55 km between Innsbruck in Austria and Fortezza in Italy, or 64 km including an existing bypass around Innsbruck, making it the world’s longest underground railway connection. Because it runs almost flat beneath the mountains, with a gradient of only 4–7 per mille, it can carry longer and heavier freight trains than the steep line over the Brenner Pass, which dates from 1867.

The main tubes were dug through at the Austrian-Italian border on 28 July 2026, with about 90% of all excavation complete. The approved cost forecast is €10.5 billion, with the EU co-funding up to 40% of the works.

The delays. The tunnel was once planned to open in 2016, then 2028. The builder now calls the end of 2032 realistic. In January 2026 the European Court of Auditors said 2032 was the earliest possible date, and found that costs across eight EU mega-projects it reviewed had risen by an average of 82% in real terms.

What changes. Trains between Innsbruck and Fortezza will take 25 minutes instead of 80, according to the tunnel company. Journeys such as Munich–Verona, now around five and a half hours, will become faster too, though by how much depends on the lines leading to the tunnel.

What the tunnels will change

Journey time in minutes today and after opening. Copenhagen–Hamburg is the planned rail time; the car crossing compares the ferry sailing with the tunnel drive.

  • Today
  • After opening
  1. Copenhagen–Hamburg by train4 h 402 h 30
  2. Innsbruck–Fortezza by train1 h 2025 min
  3. Fehmarnbelt by car45 min10 min

Source: BBT SE; Femern A/S; Hamburg Business and other reporting

The bottleneck: the lines leading to the tunnels

A tunnel is only as useful as the railway that feeds it, and here both projects hit the same problem.

  • Italy is building its southern approach in sections: Fortezza–Ponte Gardena is due around 2029, and a bypass around Trento around 2028, with more sections to follow towards Verona.
  • Germany is far behind. The plans for a new line from Munich to the Austrian border near Kufstein were sent to the Bundestag only in July 2026, with an estimated cost of up to €16.2 billion including risks and no binding timetable. Completion is not expected before the early-to-mid 2040s.
  • Fehmarnbelt faces a similar gap on the German side, with the Lübeck–Puttgarden line and the Fehmarnsund crossing both finishing after the tunnel itself.

Opening dates keep moving

  1. Brenner Base Tunnel due in 2016 (later 2028); Fehmarnbelt due in 2029.

  2. Brenner main tubes dug through at the Austrian-Italian border.

  3. Fourth Fehmarnbelt element immersed: almost 900 m of 18 km in place.

  4. Fehmarnbelt tunnel opens, road first, rail later.

  5. Brenner Base Tunnel opening described as realistic by the builder; German Fehmarnbelt rail links around 2032–33.

  6. German northern approach to the Brenner (Munich–Kufstein) expected, with no binding timetable yet.

Source: Femern A/S, Sund & Bælt, BBT SE, European Court of Auditors, German transport ministry and reporting

What it means for business travel

  • Scandinavia gets closer. A two-and-a-half-hour train between Copenhagen and Hamburg puts the two cities within day-trip range, with good onward links to Berlin, and makes rail realistic for Copenhagen–Germany meetings that are now flown.
  • Rail to Italy becomes competitive. Once the Brenner tunnel and its approaches are finished, Munich–Verona and Munich–Milan become strong rail routes. Until Germany’s approach is built, expect the full gain only south of Innsbruck.
  • Freight moves off the roads. The flat Brenner route is designed to take lorries off the motorway, which is at the centre of a legal fight between Italy and Austria over Tyrol’s lorry restrictions; the EU Court of Justice has yet to rule.

Other big cross-border rail projects are also under way: the Lyon–Turin tunnel beneath the Alps, officially targeted for 2033, and Rail Baltica between Warsaw and the Baltic capitals, where governments dropped the 2030 deadline in September 2026 in favour of a 2028–2034 window.

Until then, compare today’s options door to door with our business travel cost calculator, and see where rail already wins in our guide to train vs plane.

Comments

What do you think? No account needed. Please be kind; comments that attack people are removed.

We store only your name and comment. See our privacy policy.

    Sources

    1. Femern A/S: The Fehmarnbelt tunnel is approaching its first kilometre (28 September 2026)
    2. Femern A/S: The Fehmarnbelt tunnel will open in two stages
    3. Sund & Bælt: New phase in the Fehmarnbelt project (June 2026)
    4. Sund & Bælt: Construction costs and financing of the Fehmarnbelt link
    5. Femern A/S: EU funding (June 2022)
    6. DB InfraGO: Fehmarnbelt rail connection, route overview
    7. heise: Criticism of plans for the Fehmarnsund bridge line (July 2026)
    8. ENR: World's longest immersed tunnel passes milestone but faces delays (June 2026)
    9. Hamburg Business: Delayed Fehmarnbelt tunnel holds great opportunities for Hamburg (October 2025)
    10. BBT SE: Brenner Base Tunnel, infrastructure of the future
    11. BBT SE: Cost forecast approved, refinancing applications (May 2023)
    12. Railway Gazette: Brenner Base Tunnel main bores broken through (29 July 2026)
    13. ORF Tirol: Brenner Base Tunnel opening (2026)
    14. Euronews: Key EU transport projects set to miss 2030 targets, auditors say (19 January 2026)
    15. FS Italiane: Brenner and the Fortezza–Verona line
    16. German Federal Ministry of Transport: Brenner northern access sent to the Bundestag (July 2026)
    17. Eisenbahn Magazin: Brenner northern access, €16.2 billion and no timetable (August 2026)
    18. Court of Justice of the EU: Hearing in case C-524/24, Italy v Austria
    19. TELT: Lyon–Turin
    20. Estonian World: Rail Baltica delayed again (September 2026)

    More on work travel